04 / GOLD VALUE & COST
Conditional core gold-business model and full-process costs
Conditional calculations use the same 1 million tonnes of raw material and the mean of three original samples. The 10 newly added testing records are listed separately and have not yet entered the baseline model.
Estimated dry-equivalent quantity666,967 tonnesAverage moisture 33.303333…%; technical conversion, not an additional delivery quantity
Conditional fine-gold quantity489.442 kilogramsUniform dry-basis grade of 0.863333… grams/dry tonne, assumed recovery rate 85%
Conditional sales revenueRMB 489.4424 millionAssumed settlement price of RMB 1,000/g, with all estimated gold assumed saleable
Revenue less entered costsRMB 57.4424 millionMissing expenses not yet deducted; not net profit or distributable cash
| Cost item | Full-cycle entered amount / RMB 10,000 | Allocation / RMB·feedstock tonne⁻¹ |
|---|
| Ore material purchasing and collection | 12,000 | 120.00 |
| Logistics from ore source to transfer facility | 0 (backfilling stated as Party B's responsibility) | 0.00 |
| Transfer, drying, handling and site | 220 | 2.20 |
| Logistics from transfer site to Chenzhou plant | 15,800 | 158.00 |
| Refining and processing, reagents, energy and labor | 12,000 | 120.00 |
| Testing, downstream disposal and environmental protection | 400 | 4.00 |
| Estimated taxes | 1,800 | 18.00 |
| Equipment depreciation or construction-investment allocation | 300 | 3.00 |
| Intermediary and other project fees | 680 | 6.80 |
| Entered total | 43,200 | 432.00 |
Entered costs total RMB 432 million, equivalent to RMB 432/feedstock tonne over 1 million tonnes, or approximately RMB 647.71/dry tonne over an estimated 666,967 dry tonnes. These use different denominators for the same total; they cannot be added or substituted for actual contract unit prices at each stage. Sales, funding and financing expenses remain to be entered; estimated taxes and duplicate allocations require verification.
Uses the simple average of three original report results; the consistent dry-basis premise and 85% recovery rate both require validation. The 10 additional testing records are excluded from this model; actual processing, gold output, sales and collections are verified separately.
This page no longer uses Mine No. 1's previous calculation of 800 kilograms of gold, RMB 550/dry tonne costs and RMB 415 million balance. Construction of RMB 12 million and cash intermediary fees of RMB 3 million are budgeted separately and are not added again to the RMB 432 million cost until their coverage relationship is confirmed.
Review the full model and gold scenario calculator ↗
Source basis: project-party “Gold Capital Introduction to Gold-Associated Gold Tailings 10.5.pptx,” pages 14–17 and 28–30 (34 pages). Materials supplemented through 2026.10.05, operating data backfilled through 2026.09.29, original conditional model uses GOX 2026.10.01. Page compiled: 2026.10.06. Materials and conditional assumptions have not been independently verified.